Schedule Check Report


 

Plan Summary

Title Harbour Pointe Assisted Living Center
File name C:\Users\WoBo\Documents\Harbour Pointe Assisted Living Center.plan
Plan finish date 25/01/2018 Tasks with no progress 102
Plan remaining duration 1218 In progress tasks 18
Normal tasks 117 Completed tasks 28
Summary tasks 17 Total tasks 148
Milestone tasks 14 Resource assignments 315
Hammock tasks 0 Budget cost €60.975.810.986
Monitor tasks 0 Remaining cost €54.643.365.224
Calendars 6 Actual cost €6.509.460.170
Links 212 Total cost €61.152.825.393
Resources 37    

Report Summary

Task view All tasks
Constraints 3
Open-ended tasks (Does not include ignored links) 1
Out of sequence updates ("broken logic") 25
Lags longer than 100 units 0
Negative lags ("leads") 24
Positive lags on Finish-to-Start links 3
Start-to-Finish links 0
Lags between tasks with different calendars 0
Links to / from summary tasks 0
Duration uncertainty distribution shape 2 0
Total number of items found 56


Constraints

Schedule constraints have a significant effect on risk analysis results. They should be used sparingly, and only when the constraint reflects reality. Constraints to be particularly aware of are: • Must start on and Must finish on – preceding delays will not delay the task, and preceding time savings will not bring it earlier • Start on or after (SNET) and Finish on or after (FNET) – preceding time savings will not bring the task earlier Consider removing these constraints and replacing them with logic (e.g. Finish-to-Start links) instead. Other types of constraints are less significant because they do not influence the tasks' dates, only their floats. For example, you can use a Finish on or before constraint to indicate a desired completion date of a task – this will not force the task to finish on that day, but the shortfall will be indicated in the task's float.

Bookmark ID Description Type Constraint Type Constraint Date
EC00610-1-EC1430 Shop Drawings, Review & Approval Normal As late as possible  
EC00610-1-EC1810 Fab & Delivery Normal As late as possible  
EC00610-1-EC1180 Fab & Delivery Normal As late as possible  

Open-ended tasks (Does not include ignored links)

Options selected:Predecessors, Successors

For a schedule risk analysis to be meaningful, it is important that tasks' dates are set by logic (e.g. Finish-to-Start links) rather than constraints. This is so that the risk analysis will recognize the knock-on effect of delays. An open-ended task is one that does not have at least one predecessor and one successor – it indicates a possible lack of logic. Consider closing open-ended tasks: • If a task has no predecessor, try to find some other tasks which could potentially delay it. Leave it as open-ended if it is the project start milestone. • If a task has no successors, try to find some other tasks which it could potentially delay. Leave it as open-ended if it is a project finish or reporting milestone.

Bookmark ID Description Type Remaining Duration Detail
EC00610-1-EC1610 Curbs & Paving Normal 72 No successors

Out of sequence updates ("broken logic")

The logic in a plan can be broken when tasks have started or finished before their predecessors. It is recommended that any broken logic is removed or corrected to ensure the project schedules as expected. For example, if task A has a Finish-to-Start link to task B, but B has been started (by giving it an Actual Start date), this is broken logic. It is not clear whether B's remaining work should wait for task A to finish, or start straight away. Consider fixing the broken logic by either removing the link or removing the actual dates. Also consider using the retained logic / progress override options on the Scheduling tab of the Plan | Options dialog box.

From Task To Task  
Bookmark ID Description Type Bookmark ID Description Type Link Details
EC00610-1-EC2440 Complete Building 1 Finish milestone EC00610-1-EC2430 nm Finish milestone FS Task EC00610-1-EC2430 has already started
EC00610-1-EC2110 Demobilize Scaffolding Normal EC00610-1-EC2140 Shell Complete Finish milestone FS Task EC00610-1-EC2140 has already started
EC00610-1-EC1990 Install Railings Normal EC00610-1-EC2140 Shell Complete Finish milestone FS Task EC00610-1-EC2140 has already started
EC00610-1-EC1530 Built-Up Asphalt Roofing Normal EC00610-1-EC1780 Roof Complete Finish milestone FS Task EC00610-1-EC1780 has already started
EC00610-1-EC1540 Felt and Tile Roofing Normal EC00610-1-EC1780 Roof Complete Finish milestone FS Task EC00610-1-EC1780 has already started
EC00610-1-EC2310 Finishes, Barrier Cables & Striping Normal EC00610-1-EC2400 Complete Garage Finish milestone FS Task EC00610-1-EC2400 has already started
EC00610-1-EC2380 Punchlist Garage Normal EC00610-1-EC2400 Complete Garage Finish milestone FS Task EC00610-1-EC2400 has already started
EC00610-1-EC1860 Built-Up Asphalt Roofing Normal EC00610-1-EC2020 Roof Complete Finish milestone FS Task EC00610-1-EC2020 has already started
EC00610-1-EC1870 Felt and Tile Roofing Normal EC00610-1-EC2020 Roof Complete Finish milestone FS Task EC00610-1-EC2020 has already started
EC00610-1-EC2300 Demobilize Scaffolding Normal EC00610-1-EC2320 Shell Complete Finish milestone FS Task EC00610-1-EC2320 has already started
EC00610-1-EC2230 Install Railings Normal EC00610-1-EC2320 Shell Complete Finish milestone FS Task EC00610-1-EC2320 has already started
EC00610-1-EC2030 Unit Finishes Building South - Floor 1 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2070 Unit Finishes Building North - Floor 2 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2120 Unit Finishes Building South - Floor 2 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2150 Unit Finishes Building North - Floor 3 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2170 Unit Finishes Building South - Floor 3 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2200 Unit Finishes Building North - Floor 4 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2210 Unit Finishes Building South - Floor 4 Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2410 Final Inspections and Punchlist Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2330 Courtyard Walks and Amenities Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC2190 Complete Garage Finish milestone EC00610-1-EC2180 Complete Garage 2 Finish milestone FS Task EC00610-1-EC2180 has already started
EC00610-1-EC1200 Roadway Pavers Normal EC00610-1-EC2430 nm Finish milestone FS Task EC00610-1-EC2430 has already started
EC00610-1-EC2340 Curbs & Paving Normal EC00610-1-EC2420 Complete Building 2 Finish milestone FS Task EC00610-1-EC2420 has already started
EC00610-1-EC1270 Finish Paving, Striping and Signs Normal EC00610-1-EC2430 nm Finish milestone FS Task EC00610-1-EC2430 has already started
EC00610-1-EC1600 Site Cleanup Normal EC00610-1-EC2430 nm Finish milestone FS Task EC00610-1-EC2430 has already started

Lags longer than 100 units

Option selected: Display lags greater then 100 Days

A lag is a gap in the logic between two tasks – a delay between the dates of two tasks that are linked together. Lags cannot have risk or uncertainty. In reality it is likely that the lag represents either work or a delay, whose duration is uncertain. This is particularly significant for long lags. Consider replacing the lag with a task, so that uncertainty and risks can be assessed against it. Use the Convert Lags to Tasks tool when a project contains a large number of long lags.

None found.

Negative lags ("leads")

A negative lag is an overlap in the logic between two tasks – often it is used to represent a task starting earlier, with sufficient time allow some other work to happen. Lags cannot have risk or uncertainty. In reality it is likely that the negative lag represents an necessary overlap, whose duration is uncertain. Consider replacing a negative lag with another kind of link that does not need the lag. For example: • Replace a negative lag on a Finish-to-Start link with a positive lag on a Start-to-Start link. • Split the tasks so that the overlap is explicitly represented by a task.

From Task To Task  
Bookmark ID Description Type Bookmark ID Description Type Link
EC00610-1-EC1410 Install Exterior Windows and Sliding Glass Doors Floor 1 Normal EC00610-1-EC1490 Install Backing & Cauld Windows Floor1 Normal FS[-4]
EC00610-1-EC1410 Install Exterior Windows and Sliding Glass Doors Floor 1 Normal EC00610-1-EC1470 Install Exterior Windows and Sliding Glass Doors Floor 2 Normal FS[-5]
EC00610-1-EC1470 Install Exterior Windows and Sliding Glass Doors Floor 2 Normal EC00610-1-EC1500 Install Exterior Windows and Sliding Glass Doors Floor 3 Normal FS[-5]
EC00610-1-EC1470 Install Exterior Windows and Sliding Glass Doors Floor 2 Normal EC00610-1-EC1510 Install Backing & Cauld Windows Floor 2 Normal FS[-4]
EC00610-1-EC1500 Install Exterior Windows and Sliding Glass Doors Floor 3 Normal EC00610-1-EC1520 Install Exterior Windows and Sliding Glass Doors Floor 4 Normal FS[-5]
EC00610-1-EC1500 Install Exterior Windows and Sliding Glass Doors Floor 3 Normal EC00610-1-EC1570 Install Backing & Cauld Windows Floor 3 Normal FS[-4]
EC00610-1-EC1520 Install Exterior Windows and Sliding Glass Doors Floor 4 Normal EC00610-1-EC1650 Install Backing & Cauld Windows Floor 4 Normal FS[-4]
EC00610-1-EC1650 Install Backing & Cauld Windows Floor 4 Normal EC00610-1-EC1580 Stucco Bands Normal FS[-10]
EC00610-1-EC2110 Demobilize Scaffolding Normal EC00610-1-EC2080 Pool & Deck Normal FS[-10]
EC00610-1-EC1630 Unit Finishes Building South - Floor 1 Normal EC00610-1-EC2240 Tenant Finishes for Clubhouse Areas Normal FS[-10]
EC00610-1-EC2080 Pool & Deck Normal EC00610-1-EC2270 Pergola and Amenities Normal FS[-20]
EC00610-1-EC2270 Pergola and Amenities Normal EC00610-1-EC2360 Landscape & Irrigation Normal FS[-6]
EC00610-1-EC2090 Erect Precast Structure Normal EC00610-1-EC2250 Fountain/Water Feature Normal FS[-4]
EC00610-1-EC2280 Fire Protection and Lighting Normal EC00610-1-EC2310 Finishes, Barrier Cables & Striping Normal FS[-20]
EC00610-1-EC1870 Felt and Tile Roofing Normal EC00610-1-EC2000 Unit Finishes Building North - Floor 1 Normal FS[-5]
EC00610-1-EC1730 Install Exterior Windows and Sliding Glass Doors Floor 1 Normal EC00610-1-EC1830 Install Backing & Cauld Windows Floor1 Normal FS[-4]
EC00610-1-EC1730 Install Exterior Windows and Sliding Glass Doors Floor 1 Normal EC00610-1-EC1800 Install Exterior Windows and Sliding Glass Doors Floor 2 Normal FS[-5]
EC00610-1-EC1800 Install Exterior Windows and Sliding Glass Doors Floor 2 Normal EC00610-1-EC1890 Install Backing & Cauld Windows Floor 2 Normal FS[-4]
EC00610-1-EC1800 Install Exterior Windows and Sliding Glass Doors Floor 2 Normal EC00610-1-EC1880 Install Exterior Windows and Sliding Glass Doors Floor 3 Normal FS[-5]
EC00610-1-EC1880 Install Exterior Windows and Sliding Glass Doors Floor 3 Normal EC00610-1-EC1930 Install Backing & Cauld Windows Floor 3 Normal FS[-4]
EC00610-1-EC1880 Install Exterior Windows and Sliding Glass Doors Floor 3 Normal EC00610-1-EC1920 Install Exterior Windows and Sliding Glass Doors Floor 4 Normal FS[-5]
EC00610-1-EC1920 Install Exterior Windows and Sliding Glass Doors Floor 4 Normal EC00610-1-EC1960 Install Backing & Cauld Windows Floor 4 Normal FS[-4]
EC00610-1-EC1960 Install Backing & Cauld Windows Floor 4 Normal EC00610-1-EC1940 Stucco Bands Normal FS[-10]
EC00610-1-EC1590 Fire Protection and Lighting Normal EC00610-1-EC1680 Finishes and Striping Normal FS[-20]

Positive lags on Finish-to-Start links

A lag is a gap in the logic between two tasks – a delay after one task finishes before the next one starts. Lags cannot have risk or uncertainty. In reality it is likely that the lag represents either work or a delay, whose duration is uncertain. Consider replacing the lag with a task, so that uncertainty and risks can be assessed against it. Use the Convert Lags to Tasks tool when a project contains a large number of long lags.

From Task To Task  
Bookmark ID Description Type Bookmark ID Description Type Link
EC00610-1-EC1900 Stucco Band Trim Normal EC00610-1-EC1980 Paint Exterior Normal FS[5]
EC00610-1-EC2020 Roof Complete Finish milestone EC00610-1-EC2090 Erect Precast Structure Normal FS[5]
EC00610-1-EC2160 Stucco Band Trim Normal EC00610-1-EC2220 Paint Exterior Normal FS[5]

Start-to-Finish links

Start-to-Finish links are used deliberately very rarely, because they have the unusual effect that the successor happens before the predecessor. Consider whether this logic might be a mistake, especially if it is between tasks that are not milestones.

None found.

Lags between tasks with different calendars

Options selected:FS

A lag is a gap in the logic between two tasks – a delay between the dates of two tasks that are linked together. When the two tasks have different calendars, it is not clear which calendar the task will use – whether it is the preceding task's or the succeeding task's calendar. Consider replacing the lag with a task, so that its calendar can be explicitly defined. Use the Convert Lags to Tasks tool when a project contains a large number of long lags.

None found.

Links to / from summary tasks

Many people prefer not to put predecessors or successors against summary tasks, because other project management tools (such as Primavera P6) do not support them. Consider removing logic on a summary task, by using a milestone to represent the start or finish of all the tasks in the summary heading, and putting the link on the milestone instead of the summary task.

None found.

Duration uncertainty distribution shape

Tasks identified where: Maximum - Most Likely duration divided by the Most Likely - Minimum duration is greater than 2. The validation is only applied to the following distributions:
  • Triangle
  • Trigen
  • BetaPert
The check also tells you whether the numbers entered for Min, Most Likely and Max create a valid distribution.
A task's duration can have a "skewed" three-point estimate, which means it is not symmetrical. Usually three-point estimates are skewed on the "pessimistic" side, where the maximum is further away from the most likely than the minimum. The ratio of (Maximum - Most Likely) to (Most Likely - Minimum) is used to measure this skew. When the skew is significant (for example minimum = 1, most likely = 10, maximum = 100), this may be an indication that there are low-probability events that cause this pessimism. Consider using the risk register to represent these risks events, and reduce the amount of skew on the task's uncertainty.

None found.